1.0.1 This standard is formulated in order to adapt to the demand of the highway construction in China, construct the highway road base meet the quality requirements and avoid early damage due to poor quality of road base.
1.0.2 This standard is applicable to the construction of base and sub-base of rigid (cement concrete) pavement, semi-rigid (semi-rigid base asphalt) pavement or flexible (flexible base asphalt or medium- grade) pavement for new and rebuild highway at all classes.
1.0.3 This standard specifies the requirements on the construction / quality control of cement stabilized soil, lime stabilized soil, lime industrial waste stabilized soil, graded crushed rock, graded gravel and dry bound macadam.
1.0.4 When bituminous macadam mixture and bituminous-penetrating crushed rock are used as base, the technical requirement, construction method and quality control hereof shall meet the national standard “Code for Construction and Acceptance of Asphalt Pavement” (GB 50092).
1.0.5 When lean concrete and rolled concrete are used as base, the technical requirement, construction method and quality control hereof shall meet the requirements of the national standard “Specifications for Constructions and Acceptance of Road Concrete Pavement” (GBJ 97).
1.0.6 For all medium-grade pavement with the possibility of rebuilding for improving the grade hereof, the base structure specified in this standard shall be adopted as the main supporting course hereof, and the materials like gravel soil, screenings earth or sandy soil may be used for wearing course on the base structure.
1.0.7 The technical requirement, construction method and quality control of underlayer shall meet the requirements on sub-base of equivalent materials in this standard.
1.0.8 The maximum dry density gained by heavy compaction test shall be adopted as standard dry density in this standard.
1.0.9 The test methods involved in this standard shall meet the requirements on the testing regulations issued by the Ministry of Communications.
Contents
Contents
1 General Provisions
2 Terms
3 Cement Stabilized Soil
3.1 General Requirements
3.2 Material
3.3 Composition Design of Composite
3.4 Road-mix Method Construction
3.5 Central-plant Mixing Construction
3.6 Curing and Traffic Control
3.7 Division of Construction Organization and Working Section
3.8 Others
4 Lime Stabilized Soil
4.1 General Provisions
4.2 Materials
4.3 Composite Composition Design
4.4 Road-mix Method Construction
4.5 Central-plant Mixing Construction in Central Station
4.6 Along-road Hand Mixing Method Construction
4.7 Curing and Traffic Control
4.8 Others
5 Lime industrial waste stabilized soil
5.1 General requirements
5.2 Material
5.3 Blend composition design
5.4 Mixed in place method construction
5.5 Master station plant mixing construction
5.6 Artificial road mixing method construction
5.7 Base-curing and traffic control
5.8 Miscellaneous
6 Graded crushed rock
6.1 General requirements
6.2 Materials
6.3 Mixed in place method construction
6.4 Master station centralized plant mixing construction
7 Graded gravel
7.1 General provisions
7.2 Material
7.3 Constructions
8 Dry bound macadam
8.1 General provisions
8.2 Material
8.3 Construction
9 Quality control and inspection acceptance
9.1 General provisions
9.2 Standard test of the material
9.3 Paving test section
9.4 Quality control
9.5 Inspection and acceptance
Annex A Rebound deflection evaluation and inspection
Annex B Location Determination of Random Sampling on Site